Kiiminki BESS park connected

Published:

The second in line Enetron Park BESS power station has been connected to local power grid on Friday 30th JAN 2026. The time between the ground break and go-live was 3 months and 25 days.

The power station has now entered the testing phase, which is scheduled to take a few weeks. Commercial operation of the power station will start by the end of February.

The project timeframe and costs have manifested according to plans with no major setbacks.

The BESS power plant is provided by Finnish Cactos Oy and the main contractor of the project is Nordic Electro Power Oy.